9 Servicing |
9.1 A Tectite disconnecting tool is required for removal and servicing of certain components. |
9.2 Please ensure that the mains water and mains electrical supply are isolated prior to commencing and maintenance or replacement of components. |
9.3 Routing Maintenance: |
9.3.1 Operate appliance and check for correct function. |
9.3.2 Clean filter in Y-Pattern Strainer. |
9.3.3 Clean filters in Thermostatic Blending Valve (if fitted). |
9.3.4 Check operation of Ball Valve. |
9.3.5 Check water level in F&E Tank - ensure a minimum of 35mm below Overflow. |
9.3.6 Check that immersion heater thermostats are set to 80°C. |
9.3.7 Check for air in Heat Bank Thermal Store Pump |
9.3.7.1 Check that immersion heater thermostats are set back to 80°C and covers replaced securely upon completion. |
9.3.8 Check presence of label indicating addition of scale inhibitor. Check stored water for correct dosage of inhibitor. Details may be obtained from supplier of inhibitor |
9.3.9 Check anti-evaporation sheet fitted in F&E Tank, and that it is not obstructed. |
9.3.10 Check lid on F&E Tank is firmly secured, and as air tight as possible. |
9.3.11 Check that isolating valve on vent pipe is closed. |
9.4 Check the operation of the Primary System as follows. |
9.4.1 Check operation of programmer. |
9.4.2 Check time settings. |
9.4.3 Check heating and hot water, on and off times. Hot water should typically be set for 2 hours before demand periods. |
9.4.4 Follow any check listed in the programmer's servicing instructions. |
9.4.5 Turn both heating and hot water OFF using the programmer. |
9.4.6 Check that the primary pump is off. There may be a delay caused by a pump overrun. |
9.4.7 Take a note of the cylinder thermostat setting. |
9.4.8 Adjust the cylinder thermostat stat to MINIMUM and turn hot water ON using the programmer. |
9.4.9 Check the primary pump is OFF. |
9.4.10 Turn up the cylinder stat until it switches. The primary pump should switch on as well as the boiler. |
9.4.11 Turn the room stat up to maximum and turn the central heating ON using the programmer. |
9.4.12 Check the mid-position valve swings across to mid-position. |
9.4.13 Turn the cylinder thermostat to MINIMUM. |
9.4.14 Check the mid-position valve swings completely across to heating. |
9.4.15 Reset the cylinder stat to the required setting, typically 75°C. |
9.4.16 Reset the programmer to original settings. |
9.4.17 Reset the room stat as required. |